Kizad Heavy-Load Parking

Kizad Heavy-Load Parking
Location
Kizad, Abu Dhabi
Type of work
Roadworks and parking

Parking built to carry loads of up to 1,000 tons, from formation level to base course.

Scope of work

  • Formation level made by scraping the existing ground, then watering and compaction to 95% MDD.
  • Subgrade spread at 15 cm thickness, watered and compacted to 98% MDD.
  • Sub-base placed, watered and compacted to 100% MDD with CBR above 80, per drawings.
  • Base course 15 cm thick with CBR above 60, per specifications.